The vastness of the Panama Canal construction site, which is almost one mile long, complicates the transfer of concrete.

The Concrete Canal

The Concrete Canal

  • The vastness of the Panama Canal construction site, which is almost one mile long, complicates the transfer of concrete.

    http://www.theconcreteproducer.com/Images/tmp594C%2Etmp_tcm77-1877555.jpg

    true

    The vastness of the Panama Canal construction site, which is almost one mile long, complicates the transfer of concrete.

    600

    Teake Zuidema

    The vastness of the Panama Canal construction site, which is almost one mile long, complicates the transfer of concrete.

  • Image

    http://www.theconcreteproducer.com/Images/tmp62F2%2Etmp_tcm77-1877561.jpg

    true

    Image

    600

    Teake Zuidema

  • Concrete is transported from the batch plant to the point of placement by ready-mix trucks, agitator trucks, pumps, conveyors, central placing towers, and buckets.

    http://www.theconcreteproducer.com/Images/tmp8478%2Etmp_tcm77-1877581.jpg

    true

    Concrete is transported from the batch plant to the point of placement by ready-mix trucks, agitator trucks, pumps, conveyors, central placing towers, and buckets.

    600

    Teake Zuidema

    Concrete is transported from the batch plant to the point of placement by ready-mix trucks, agitator trucks, pumps, conveyors, central placing towers, and buckets.

  • A conveyor delivers concrete to the site, which, in places, is a maze of rebar.

    http://www.theconcreteproducer.com/Images/tmp50B0%2Etmp_tcm77-1877549.jpg

    true

    A conveyor delivers concrete to the site, which, in places, is a maze of rebar.

    600

    Teake Zuidema

    A conveyor delivers concrete to the site, which, in places, is a maze of rebar.

  • Agitator trucks dump concrete into the hopper, which provides a steady feed to the conveyors.

    http://www.theconcreteproducer.com/Images/tmp4787%2Etmp_tcm77-1877542.jpg

    true

    Agitator trucks dump concrete into the hopper, which provides a steady feed to the conveyors.

    600

    Maxon Industries

    Agitator trucks dump concrete into the hopper, which provides a steady feed to the conveyors.

  • Image

    http://www.theconcreteproducer.com/Images/tmp6C59%2Etmp_tcm77-1877567.jpg

    true

    Image

    600

    Teake Zuidema

  • Insulated agitator truck bodies equipped with roll-back tarps keep the concrete produced at the batch plant at super-cooled temperatures.

    http://www.theconcreteproducer.com/Images/tmp7553%2Etmp_tcm77-1877571.jpg

    true

    Insulated agitator truck bodies equipped with roll-back tarps keep the concrete produced at the batch plant at super-cooled temperatures.

    600

    Maxon Industries

    Insulated agitator truck bodies equipped with roll-back tarps keep the concrete produced at the batch plant at super-cooled temperatures.

  • Some hard-to-reach places are served by tower-crane mounted conveyors.

    http://www.theconcreteproducer.com/Images/tmp7D62%2Etmp_tcm77-1877576.jpg

    true

    Some hard-to-reach places are served by tower-crane mounted conveyors.

    600

    Teake Zuidema

    Some hard-to-reach places are served by tower-crane mounted conveyors.

 

The world’s largest ongoing construction project is the expansion of the Panama Canal, adding a third lane to allow larger ships to traverse the isthmus. The joint venture that is building the new locks and dams has demanded an extra $573 million for the job. Making the right concrete mix was its greatest challenge.

In 2009, Grupo Unidos por el Canal (GUPC) won the contract to build larger locks on both entrances of the Panama Canal with a low bid of $3.1 billion. The joint venture is formed by Spanish contractor Sacyr Vallehermoso, Italian Impregilo, Belgian Jan de Nul, and Panama’s Constructora Urbana. Most of the excavation (a total of 45.5 million cubic yards) is now complete, and the project is mainly about placing rebar and casting concrete. However, GUPC is six months behind schedule due to problems with producing the right mix for the marine concrete.

The requirements from the Panama Canal Authority (ACP) are high since the operator of the canal wants a design-life of 100 years in an area that is seismically active. This means, among other things, that saltwater cannot reach the rebar embedded in the marine concrete during that period. “It took GUPC six months before they came up with a concrete that passed the ASTM C1202 test for marine concrete,” says Abdiel Julio, of ACP’s public relations department. GUPC claims ACP misstated the quality of the basalt aggregate and was slow in approving the mix. It is demanding the $573 million to compensate for unforeseen costs.

“The problem was that the crushed basalt out of the excavation that we used as aggregate contained much more fines than we were led to believe,” says Jan Kop, the Dutch project manager for Jan de Nul. The giant crusher GUPC built on the Pacific side of the canal has to remove 30 percent of the fines from the basalt. “Our concrete mix passed the test after we removed more fines and added more cement and silica fume to make it more impermeable,” says Kop.

Concrete production

The two concrete plants on both construction sites are humming along now, and together, produce 160,000 tons of concrete per month. In all, the project will need 6.5 million cubic yards of concrete and 250,000 tons of reinforcing steel. Both sets of locks consist of three lock chambers that each are 140 feet long, 180 feet wide, and 59 feet deep. Although they are larger than the existing locks, they will use less water. A gravity-based system of saving basins, water tunnels, and culverts makes it possible to recycle 60 percent of the water from each passing ship.

Both concrete plants are designed to produce 21 yards in five minutes. With ambient temperatures reaching 37 degrees C (100 degrees F), temperature control is essential and all concrete production, transport, and casting is embedded with cooling systems. According to specifications, the temperature of the mix must be within 7.7 degrees C (14 degrees F) at all times. Forced cooling systems on both sides are capable of making 670 tons of ice each day. Huge tents prevent the sun from warming the sand and the coarse aggregate.

The heavy traffic and the vastness of the almost one-mile-long site complicates the transfer of the concrete. A fleet of open-bed, nine-yard trucks, conveyor belts, and concrete pumps transports the concrete. Most concrete is delivered to its final destination by a Putzmeister TB130 telescopic belt conveyor or its bigger cousin, the TB200. Some hard-to-reach places are served by tower-crane mounted conveyors. More than 21 million square feet of concrete must be formed.

Panama gets a lot of rain, which is good for the canal but a problem for casting concrete. “We cast the concrete in layers with one low point,” says Kop. “When it rains, all of the water runs to the lowest point from where we can easily remove it. When it rains for a long period, we stop pouring, and then we have to deal with an unforeseen cold joint that demands extra attention before we can move on.”

The ACP had planned to open the expanded canal in October 2014, 100 years after completion of the original canal. The opening is now expected to be in spring 2015. GUPC faces penalties of $300,000 for every day the project is delivered after Oct. 21, 2014. Once the new locks are open, Post-Panamax ships, much larger than those that currently navigate the canal and carrying 12,600 containers, will traverse the famous waterway. TCP

Teake Zuidema is a Dutch freelance photographer/journalist living in Pittsburgh.